Electrifying
Kano (II)
BY
Abubakar Jika
Some
times in September last year I came out with Electrifying Kano, a write up that
attempted to verify the electrification claims of Governor Rabiu Musa Kwankwaso.
This arose out of two developments. First, the persistent claims by the
Kwankwaso regime that within two years it electrified more towns and villages
than it met. The second was the apparent endorsement of this claim by the
National Media Tour, whose spokeswoman openly advocated Kwankwaso to “Tazarce”
I was a witness to the second incident.
There
were several reactions to that article. There were those who saw it as another
media endorsement of Kwankwaso. Some privately complained to me that the article
would burnish the image of the Governor. There were of course those who hailed
the write up. Among this group are those who believe in Kwankwaso and who hail
any write up that appears to favour him. The others were those who saw in it
investigative journalism. After all it was a sampling technique and I could not
sample more than the few I did.
In
any case, in this our profession you cannot satisfy all. It is not even the
business of a journalist to try to satisfy any one. His business is to report on
what he saw. He is free to comment, but facts are sacred. To prove my
investigation was factual, the National Media Tour, which investigated all
states except those controlled by the AD party, gave Kwankwaso a National Award
on rural
electrification.
In
any case, the conclusion of my electrifying Kano was “
I intend to check on other locations, perhaps next year”. The idea was
to put the Agency responsible- Kano State Rural Electricity Board - headed by
Eng. Ahmed Ishaq on its toes. That there are societal watches dogs, following
their footsteps.
In
my first outing during my visit to Zoza Electrification Project in Rogo local
government area I observed that only half (50 percent) of the job was completed
then. It was billed to cost N10 million. I went back to that project. The
project has been completed. When I visited Farin Dutse ElectrificationProject in
Sumaila local government in September last year, it was at preliminary stages or
about 20 percent. It was estimated to cost N5.7million.
I
observed then that the pace of work there was rather slow, perhaps due to heavy
down pour of August. I was a bit critical of the slow pace of work then.
This
time when I went back it was completed. I was surprised. I was told it was a
joint project. I don’t know whether my observation then aided the pace. But
looking at the performance chart of the Board I observed that the project was
billed to be completed by the end of last year.
I
also observed and reported on the Ningawa Electrification Project in Madobi
local government Area then that nothing serious was done there. I was told it
was a new project. Also the August rainfalls might have contributed to the
sluggish pace I noted then. During my follow up visit, it was still not
completed. However appreciable progress has been made. I estimated the level of
work done to be about 55 percent.
I
was also told it was a joint project. Now that we are in dry season, except if
it is funding problem, one hope that it would be completed before the onset of
rains in three months time. The project is relatively big, which I was told
costs N 11.8 million. I noticed equipment on site.
I
choose five other local governments for sampling this time around. These are
Bebeji, Ajingi, Kumbotso, Garun Malam and Wudil. I thought these are fairly
representative enough sampling for this report. As we all know, random sampling
is a globally accepted technique in research. I went to these locations.
At
Bebeji local government I went to Kofa. The Kofa Electrification Project is
completed. I was told the state government solely sponsored it. I also went to
Anadariya. Its project was also completed.
I was told it was financed completely by the state government.
The quality of job was good. I was not told the cost.
At
Ajinqi I went to two places. I was at Toranke. The project is not completed. I
estimated it to be about 60 percent. I also do not know how much it costs. I was
also at Kwashi. There again the project was not completed. I was however told it
cost about N8.6 million. I was told the state government is sponsoring the
project. The pace of work is not as fast as Toranke. Nobody offers explanation
for this.
At
Kumbotso local government I went to two locations. I was at Sabuwar Gandu. The
Electrification Project was completed. I was told it cost N9.4 million. I was
told the state government solely funded it. It looks quite impressive.
I
also visited Shekar Maidaki. The project is on going. I was told it would cost
about N7 million. The project has gone far. I estimate it would be up to 70
percent. But when I went on site that day, the workers were not many. Those I
saw were not willing to answer specific questions on completion dates. They
referred me to “Oga
Engineer”, who I could not locate. I went to two places at Garum Malam
local government. I was at Dumaje. The project was completed. I was told it was
a state government project. The quality appears good. I proceeded to Unguwar
Kudu. The project there was also completed. Again I was told it was a state
government affair. I could however not get financial figures at both Dumaje and
Unguwar Kudu. I was advised to check on the State Rural Electricity Board in
Kano.
I
rounded my visit at Wudil local government. I was at Indabo. The project was on
going. It was about half completed. I could not however get specific figures on
cost. I went to Kausani. The project is also on going. I was told it would cost
slightly less than N10 millions. The pace of work appears good there too.
Perhaps the project would be completed before April rains.
For
a state that prides itself as “center of commerce”,
it appears the government appreciates the significance of electric energy. No
area can industrialize or engage in any viable commerce without electricity
supply. This is one area of growing consensus, as exemplified by the Media Tour
Awards, which Kwankwaso has done well on.
I
rounded my trips with a visit to Engineer Ishaq Ahmed Permanent
Secretary/Managing Director State Rural Electricity Board to solicit his
comments on the “secret behind”, their success. Again he declined extensive
interview preferring their work to speak for them.
He however told me that performance and integrity were two heritage of their Board, which was passed through the various leadership tenures. He worked over 20 years there and shares the glory with his predecessors. Such humble generosity and consistency are traits we need to pass from one leadership to another if we are to break out of the cull – de sac we find ourselves in Nigeria.
JIKA teaches at the Dept. of Mass Communications, Bayero University, Kano.